Hi

On the page application/core_al_app_provider_summary.xsl, I'm trying to assign a criticality to the processes listed in the Supported Physical Processes section. I've used the Launchpad spreadsheet to perform the upload and I have filled the Criticality of Application Service column on the Business Process 2 App Services tab. From Protege I can see slot APP_SVC_TO_BUS_RELATION/Business_Criticality (App To Process Business Criticality) is populated as per the spreadsheet however, it's not being displayed on the webpage. Am I looking at the correct slot?

Interestingly, importing the contents of the Launchpad has created three new entries in Business_Criticality with names High, Medium and Low however, the ones already present are prefixed with 'Business Criticality:' I've tried using both but neither appear to show on the webpage. I don't think this is the issue.

Thanks
Ben